New modification proposalCMP248 Enabling Capital Contributions for Transmission Connection Assets during Commercial Operation 26 August 2015 Eneco raised CMP248 Enabling Capital Contributions for Transmission Connected Assets During Commercial Operation on 23 July. The modification seeks to enable users to make a contribution to the capital component of the transmission connection assets after commercial operation of a power station has begun. Currently the CUSC contains provision for such contributions to be made only at the time of commissioning, either in full or in part. The proposer said the modification would give users more choice, enabling them to reflect changes in their circumstances and to ...