Transmission Charging Methodologies Forum 8 October 2020 Assessment  Headlines The locational security factor is currently 1.8. It is reviewed at each price control period and fixed for the duration. The Electricity System Operator (ESO) has previously stated that it expects it to remain at 1.8 for the RIIO-2 period. The ESO informed the meeting that an internal legal review is being undertaken to establish the detailed process by which the degree of accuracy is determined. Following this, it may be appropriate to consult more widely with stakeholders before any final decisions are made. The ESO continues to seek a full dataset from the ...