Issue 1075 | CUSC Workgroup meeting on CMP328 Connections Triggering Distribution Impact Assessment

CUSC Workgroup Meeting: CMP328 Connections Triggering Distribution Impact Assessment Headlines The meeting reviewed the workgroup consultation responses and any matters arising. 11 responses were received with most supportive of the distribution impact assessment concept. Views varied as to the use of a 1MW threshold, implementation timescales, inclusion of embedded users with/without transmission entry capacity in any assessment, who should bear any costs and the trigger for the process. The proposer clarified its preferences for each of these in the original proposal. It considered that there were no direct DCUSA implications and therefore no consequent modifications required. The Electricity System Operator (...