Editor’s Pick | Ofgem delays Transmission Demand Residual change to 2022

The regulator has accepted a request by National Grid ESO (NGESO) to replace the current CUSC proposal to implement the Targeted Charging Review (TCR) decision for a fixed residual transmission network use of system (TNUoS). A new implementation date of 1 April 2022 will replace 1 April 2021.

NGESO submitted a letter to Ofgem on 25 March to withdraw CMP332 Transmission Demand Residual Banding and Allocation (TCR), saying that during the workgroup process and workgroup consultation “significant issues have been raised that question the value and impacts to consumers”. It highlighted two specific issues:

  • The lack of visibility to the workgroup of modelled tariffs, due to the necessary data not being available until very recently from market participants. This meant suppliers and system users could not understand the impact of the methodologies proposed and that consideration of alternatives was not possible.
  • The impact on the short-term realisation of consumer benefits, due to the short notice of the draft final charges in late 2020 which provides little time for suppliers to understand impacts, adjust their business models and pass on the consumer benefits.

NGESO asked for withdrawal to give further time for the issues raised in the workgroup to be considered and for a review of the impacts and the implementation timescales.

In its response on 31 March, Ofgem consented to the withdrawal and directed NGESO to raise a new proposal to enable the reforms to TNUoS to take effect from 1 April 2022. The regulator stressed that this decision affected only the transmission demand residual (TDR) element of its TCR decision and that all the other elements will progress as in its original Directions. Ofgem said that in coming to its decision on the TCR in November, it anticipated around £50mn in benefits to consumers from implementing TDR reforms in 2021 compared to 2022. It also expected realisation of these benefits could be limited due to the time needed for suppliers to pass them onto consumers.

Since the decision, it said several suppliers and large energy consumers had provided it with detailed information on the difficulties arising from the lack of certainty in 2021 TDR charges in the non-domestic market. These arise due to accurate charges for April 2021 not being available until late 2020 and the increasing view in industry that the TDR timeline contains significant risks, and also that the charges may not be delivered on time. It noted the relatively short period allowed for the implementation of the new IT systems and charging processes.

Ofgem said it understood that there is a large variation in how suppliers are dealing with the uncertainty around TDR charges, with some suppliers having signed, or are continuing to sign, a significant number of non-domestic contracts for 2021 that do not take account of the expected TDR changes.

On average, TDR charges will increase for non-domestic and decrease for domestic consumers. Therefore, Ofgem is concerned that suppliers continuing to contract with customers without taking account of the TDR reforms will either lead to these suppliers incurring losses, or to suppliers triggering re-opener clauses in their contracts to increase these charges. It said this could lead to disruption for some non-domestic consumers and mean that suppliers may need to re-open many non-domestic contracts to recover the additional charges. This outcome could lead to a significant level of disputes, re-contracting and switching. It could also put some suppliers under financial strain, particularly those whose portfolios lack diversity or who rely on a small number of large contacts for a significant proportion of their revenue.

The regulator has therefore concluded a one-year delay is in the best interests of consumers and that it would also reduce pressures on industry and consumers in the coming months, so facilitating implementation of the TCR embedded benefit changes due in April 2021.

The risks from the short implementation timescale were evident at an early stage. While the decision now aligns the dates for changes to transmission and distribution use of system residual charges, COVID-19 could force further timeline changes as industry and the regulator re-prioritises.

If you have enjoyed reading Nick’s views and want to read about the latest developments in the energy market, please contact us for a month’s trial of Energy Spectrum.

Energy Spectrum is a weekly publication covering all of the key policy, regulatory, market and transactional developments across the energy sector. It offers a timely, insight-driven overview of the need-to-know news and changes in the energy sector. Contact the Editor, Nick Palmer to request a trial on 01603 604400.

Related thinking

Low carbon generation

Latest developments in the TPI space

We recently published our 2023 Annual TPI report which provides an independent review and analysis of the market for TPIs, and the services provided by them. The report also looks at the current challenges and opportunities for TPIs, such as regulatory changes, competition with suppliers, and diversification of services. 2023...

Power and gas networks

Considerations for forecasting non-commodity costs for large users

Electricity non-commodity costs, also known as Third Party Charges (or TPCs), are faced by the vast majority of end consumers that use electricity. They represent a significant proportion of the energy bill for domestic, SME and large industrial user types; however, their applicability and scale can vary depending on the...

Regulation and policy

What’s going on with REGOs?

Renewable Energy Guarantees of Origin, more commonly referred to as REGOs, are certificates issued to accredited renewable generators for every MWh of electricity they produce over a year period. The initial intentions of these certificates were to provide suppliers a means to prove the level of renewable generation they received...

Home supply and services

Ofgem strives to improve consumer experiences across both the domestic and non-domestic sectors

Over the last week, a number of anticipated publications were issued by Ofgem that hold the potential to make a significant change to the requirements on both domestic and non-domestic suppliers. The findings of Ofgem’s non-domestic market review were revealed, alongside a policy consultation on the options available to address...

Energy storage and flexibility

Waiting to connect: the problems and solutions for network connection queues (Part 2)

Network connection queues continue to be a notable topic of interest as many generators face significant delays to project development – an issue that is directly conflicting with net zero ambitions and recent focuses on strengthening domestic energy supplies. In Part 1 of our two-part series on connection queues we...

Home supply and services

Addressing consumer harms in the non-domestic market

In recent months, Ofgem has shone a light on areas across both the domestic and non-domestic market where suppliers could improve their practices for customers and go beyond what they are obligated to do in the licence conditions. In a time of significant and extended volatility, the regulator has brought...

Energy storage and flexibility

Waiting to connect: the problems and solutions for network connection queues

The number of grid applications has risen significantly in recent years, resulting in increased pressure on the electricity networks to facilitate new connections. In its Energy Security Strategy, the UK government set out ambitions for 95% of electricity to be sourced from low carbon generation by 2030, and for the...

Energy Market Design

Are prices going to rise in Contracts for Difference Allocation Round 5?

A number of factors may be about to put an end to the trend for falling energy prices in the Contracts For Difference (CfD) scheme. The CfD scheme has provided strong subsidy support whilst also providing consumers robust levels of protection. High investor confidence and steady reductions in capital costs...