Ofgem’s Network Access and Forward Looking Charges review – should I be interested

Spoiler – if you are a distribution connected generator, yes, In a big way

Ofgem is currently progressing one of its biggest overhauls of network charging; with the Targeted Charging Review having only recently concluded that is quite a statement. We have already seen the value to distribution connected generators of exporting at peak reduce significantly through the introduction of the Embedded Export Tariff, soon to be followed by the value of reducing demand at peak times (so-called “Triad avoidance”) reducing dramatically from April 2022 if industry code modifications go to plan.

But that is just the start

Ofgem has now turned its full attention to its Network Access and Forward Looking Charges Significant Code Review (a bit a mouthful –so let’s go with the Access SCR) which could have even bigger impacts for distribution connected generators.

Generators connected to the distribution network currently benefit from two value streams:

  • Albeit much smaller than the Transmission Network Use of System (TNUoS) embedded benefit used to be, the Embedded Export Tariff (EET) still provides some value for generators in the South of the country who export at peak times. Crucially, it is “floored” at zero, so those in the North and in Scotland don’t face an EET charge – the thinking being that to expose generators to an EET charge would incentivise them to reduce output at peak, distorting the wholesale market
  • Distribution Use of System (DUoS) credits (commonly known as “generator” DUoS or GDUoS), particularly for those connected to the lower voltages of the distribution network (at 11kV and below) can also be lucrative. This is particularly the case for generators who can operate in the peak “red” time periods. They are the same within each distribution region and throughout the year, albeit they do vary by time of day with low credits overnight, mid-range credits in the working day and high credits in early evening.

Both of these are now up for debate, with potentially significant consequences

Firstly, on the EET. Ofgem’s central option under the Access SCR is to charge distribution connected generators in the same way as their transmission connected counterparts are charged – namely on a capacity basis. The regional differentiation is broadly similar – those in the South East benefit from credits while those in the North of England face small charges and those in North Scotland face high charges. But the big difference is that the protection of the EET “floor” would disappear, so generators in the North would be exposed to a new cost item which they currently avoid. They would also be exposed to the raft of uncertainty currently faced by transmission connected generators (take a look at the number of active Connection and Use of System Code (CUSC) modifications looking at how TNUoS should be charged and you’ll get the picture).

Secondly, on DUoS. Under the Access SCR, Ofgem is seeking to introduce much greater locational granularity to charges and credits. This would mean charges varying by location depending on the state of the network in that location within the DNO region. Most notably for generators, this could mean the removal of “blanket” credits in all locations and instead result in charges at certain times in areas which are considered “generation dominated” at those times. This isn’t all bad – generators in heavily demand dominated areas could see additional benefit in the form of higher credits, and flexible generators may be better off if the increase in locational granularity is also coupled with an increase in the sharpness and variability of time of use signals. But this potential change could be a shock for those in generation dominated areas who find themselves exposed to a new cost.

Don’t despair

Navigating the impacts of these changes can be extremely challenging and we are continually monitoring developments to ensure we can provide our clients with the best data available to help manage these uncertainties. Our long-term 15-year forecasting of generation TNUoS charges (including sensitivities to all those ongoing CUSC modifications) makes sure you have a clear picture of the scale of the challenge if Ofgem were to introduce TNUoS charges on distribution connected generators. Added to this, our site-specific assessments of the state of power flows on any given section of the DNO network can help you understand the direction of travel for DUoS credits.

For further information on how our network cost and revenue forecasting can enable you to make better operational and investment decisions, please get in touch with Andrew Enzor on a.enzor@cornwall-insight.com.

Related thinking

Low carbon generation

Latest developments in the TPI space

We recently published our 2023 Annual TPI report which provides an independent review and analysis of the market for TPIs, and the services provided by them. The report also looks at the current challenges and opportunities for TPIs, such as regulatory changes, competition with suppliers, and diversification of services. 2023...

Power and gas networks

Considerations for forecasting non-commodity costs for large users

Electricity non-commodity costs, also known as Third Party Charges (or TPCs), are faced by the vast majority of end consumers that use electricity. They represent a significant proportion of the energy bill for domestic, SME and large industrial user types; however, their applicability and scale can vary depending on the...

Regulation and policy

What’s going on with REGOs?

Renewable Energy Guarantees of Origin, more commonly referred to as REGOs, are certificates issued to accredited renewable generators for every MWh of electricity they produce over a year period. The initial intentions of these certificates were to provide suppliers a means to prove the level of renewable generation they received...

Home supply and services

Ofgem strives to improve consumer experiences across both the domestic and non-domestic sectors

Over the last week, a number of anticipated publications were issued by Ofgem that hold the potential to make a significant change to the requirements on both domestic and non-domestic suppliers. The findings of Ofgem’s non-domestic market review were revealed, alongside a policy consultation on the options available to address...

Energy storage and flexibility

Waiting to connect: the problems and solutions for network connection queues (Part 2)

Network connection queues continue to be a notable topic of interest as many generators face significant delays to project development – an issue that is directly conflicting with net zero ambitions and recent focuses on strengthening domestic energy supplies. In Part 1 of our two-part series on connection queues we...

Home supply and services

Addressing consumer harms in the non-domestic market

In recent months, Ofgem has shone a light on areas across both the domestic and non-domestic market where suppliers could improve their practices for customers and go beyond what they are obligated to do in the licence conditions. In a time of significant and extended volatility, the regulator has brought...

Energy storage and flexibility

Waiting to connect: the problems and solutions for network connection queues

The number of grid applications has risen significantly in recent years, resulting in increased pressure on the electricity networks to facilitate new connections. In its Energy Security Strategy, the UK government set out ambitions for 95% of electricity to be sourced from low carbon generation by 2030, and for the...

Energy Market Design

Are prices going to rise in Contracts for Difference Allocation Round 5?

A number of factors may be about to put an end to the trend for falling energy prices in the Contracts For Difference (CfD) scheme. The CfD scheme has provided strong subsidy support whilst also providing consumers robust levels of protection. High investor confidence and steady reductions in capital costs...