How much Raise FCAS is needed as inertia reduces?

The Step Change scenario in the 2022 Integrated System Plan (ISP) is targeting 83% renewable energy generation in the NEM by 2030-31. By then, around 79GW of VRE resources (wind, utility solar, and distributed PV) is expected to have been installed to help replace the 14GW capacity of synchronous generation withdrawn.

Increased generation from VRE resources and a decrease in synchronous generation installed will result in the reduction of system inertia. System inertia is the ability of synchronous generators to resist frequency changes by virtue of their rotating mass. The lower the system inertia, the faster the frequency deviation is after a contingency event, such as a power station unexpectedly going offline. Primary frequency response and contingency ancillary raise services may help arrest the frequency during such events. However, with higher Rate of Change of Frequency (RoCoF) thresholds, there is less time for PFR to respond, leaving contingency raise services to pick up the slack.

In this Chart of the Week, we examine the effect of a decrease in system inertia and the amount of contingency raise service, specifically Raise 6-second (R6), that may be needed for frequency restoration.

Source: AER, Inertia Requirements Methodology

Figure 1 shows an increasing trend in R6 enablement starting in 2019-20. This increase, however, is not due to a decrease in inertia levels but is due to a stepping down in load relief from 1.5% to its current value of 0.5%. Load relief is the assumed change in load that happens when system frequency changes. Also shown in Figure 1 are three scenarios of projected R6 requirements, with these general assumptions; the Largest Credible Risk (LCR) will be set by Kogan Creek and low load conditions of 18,860 MW.

ScenarioDescriptionMethod to calculate R6 requirement
1Business as usualR6 requirement based on LCR and load relief
2LCR + Inertia  (Typical) responseR6 requirement will consider decrease in typical and minimum threshold inertia levels. First, the projected system inertia level was estimated based on typical sub-region inertia values and projected based on the trend of decreasing sub-region inertia levelsuntil 45,350 MWs. From then, the projected inertia referenced R6 requirement will be calculated.
3LCR + Inertia  (Minimum) response

Under scenario 1, a static requirement of 655MW, LCR & 0.5% Load Relief may not be sufficient to restore the system to a frequency level acceptable to the Frequency Operating Standard. In order to solve this problem, the relationship between R6 requirement and system inertia levels was used to project future R6 requirements for scenarios 2 and 3. For the years 2023-2024, the R6 requirement is set at 1,195MW for scenario 2 and 1,328MW for scenario 3, already double that of static requirement, and continues to increase to 1,519MW by 2027-28.

While increasing the contingency raise service can help restore frequency in cases of low inertia level, it may not be economical to increase the requirement to more than double the current enablement levels. The upcoming Very Fast FCAS market, which will commence on 9 October 2023, is expected to alleviate the potential increase in R6 requirement brought about by low system inertia conditions. Synchronous generators that provide physical inertia and synchronous condensers with flywheels can also be alternative ways to deal with low system inertia conditions.

Cornwall Insight Australia has an in-house FCAS forecast model that considers these potential scenarios. Our model is based on engineering techniques and assumptions, leveraging our extensive experience, comprehensive research, and independent perspective on relevant areas. For more information on power and market modelling or other consultancy products, please contact enquiries@cornwall-insight.com.au.


To keep reading, please log in to your account

Related thinking

Energy storage and flexibility

R1 and L1 revving up the BESS revenues

In our ‘The VFF… Very Fast and Financially rewarding market so far’ Chart of the week, the two new contingency markets, the Very Fast raise contingency FCAS market and the Very Fast lower contingency FCAS, were analysed and demonstrated the high participation of big batteries along with VPPs and DERs....

Low carbon generation

An investigation into REZ capacity factors during Victoria’s dark doldrums

As the grid transitions to much higher levels of renewable penetration, the range of generation outcomes on any given day increases. The worst of these ranges are known as dark doldrums when there is a combination of poor conditions for wind and solar generation, usually a windless day in winter....

Commercial and market outlook

The VFF… Very Fast and Financially rewarding market so far

On 9 October 2023, 1pm (market time), we saw the start of two new contingency FCAS markets. The Very fast raise contingency FCAS market, and the Very fast lower contingency FCAS. Upon commencement of the VF FCAS market, a commissioning period of two weeks with an initial max requirement of...

Commercial and market outlook

Is the sun setting on utility solar?

The Federal Government has legislated emissions reductions of 43% below 2005 levels by 2030. Sourcing electricity from renewable technologies is fundamental to meeting this, with a much-publicised target of 82% renewables in the grid by 2030 – up from a current value of 38% over the last year. Fortunately, the...

Commercial and market outlook

The Very Fast FCAS market is about to commence – a look at a possible time-of-day profile for R1

On 9 October 2023, 1pm (market time), the dispatch of the new Very Fast (VF) FCAS market in the NEM will commence and will add two new markets for contingency FCAS, Raise 1 (R1) and Lower 1 (L1). AEMO has released a final industry go-live plan to keep track of...

Low carbon generation

“Ooh, a storm is threatening, My very [interconnection] today”: Can states utilise interconnection to share wind resources?

Penetration of renewables continues to dominate the energy news, as we saw renewables as a proportion of total demand reach new heights this week to a new record of ~70% penetration. In light of this continuing march toward a renewable-dominated grid (building on some analysis we did in Chart of...

Energy storage and flexibility

How long is the ‘Golden time of day’ for batteries?

A key part of the business case for grid-scale standalone batteries is the arbitrage opportunity between low daytime wholesale prices (when renewable energy generation from solar is plentiful) and high evening prices (when the sun goes down and household demand ramps up quickly). The share of battery revenue coming from...

Low carbon generation

MLF changes in NSW in the past decade

MLF, short for Marginal Loss Factor, represents the portion of electricity losses that occur along the transmission network between a connection point and the Regional Reference Node (RRN). Within the NEM, the MLF serves as a metric to quantify these losses along the network, playing a pivotal role in determining...