“If everything seems under control, you’re not going fast enough.” – Mario Andretti


Over the past few months, there has been an avalanche of announcements related to the energy market. Victoria wants to be 65% renewable by 2030 and 95% by 2035, AGL is likely to retire Loy Yang A ten years earlier, Queensland has its Energy and Jobs Plan, and transmission investment projects are getting financial support from the governments.

These announcements validate the insight from AEMO’s latest Integrated System Plan (ISP) and the industry’s expectation that the National Electricity Market (NEM) is transitioning to a lower-emissions future faster than expected. The transition is driven by many factors: economics, affordability, environmental ambitions, social license, reliability, and system security.

While we all understand the importance of this transition, the pace at which we act on it also becomes increasingly critical, if not the most critical. In this Chart of the week, we ask: is the industry acting fast enough to meet the requirements of this transition?

The answer is simple: not yet.

From now until 2050, according to the 2022 ISP Step Change scenario, the NEM must add at least ~5,000 MW of large-scale Variable Renewable Energy (VRE) and Battery Energy Storage and System (BESS) year-on-year. However, according to registration data from AEMO’s Nemweb, over the past five years, the NEM has only been building about 3,000 MW, on average, of new capacity year-on-year. While this figure has been record-breaking in terms of additional penetration of new capacity, predominantly VRE and BESS, it is still slower than the required pace at which we must commission new capacities to meet the ISP projections.

If we keep going at this pace, ~2,000 MW behind the required build-out year-on-year, it is equivalent to retiring a full Loy Yang A power station (installed capacity value) every year. On this basis, we would soon find ourselves in a precarious situation. This analysis is also exclusive of the potential shortfall in projected annual installed capacity from the distributed network, which could make this total shortfall even larger

Of course, the reasons why we are building slower than how we need to and how we could expedite it is a much broader equation to solve than what we can put in this diagram; and it is also a separate discussion to have. Nevertheless, while we have begun to put new mechanisms in place to expedite new capacity, more support will likely be needed to get capacity to market sooner. We are already behind the curve, and the point stands currently, we are underperforming.

For more information on our services, please contact us at enquiries@cornwall-insight.com.au.

To keep reading, please log in to your account

Related thinking

Energy storage and flexibility

R1 and L1 revving up the BESS revenues

In our ‘The VFF… Very Fast and Financially rewarding market so far’ Chart of the week, the two new contingency markets, the Very Fast raise contingency FCAS market and the Very Fast lower contingency FCAS, were analysed and demonstrated the high participation of big batteries along with VPPs and DERs....

Low carbon generation

An investigation into REZ capacity factors during Victoria’s dark doldrums

As the grid transitions to much higher levels of renewable penetration, the range of generation outcomes on any given day increases. The worst of these ranges are known as dark doldrums when there is a combination of poor conditions for wind and solar generation, usually a windless day in winter....

Commercial and market outlook

The VFF… Very Fast and Financially rewarding market so far

On 9 October 2023, 1pm (market time), we saw the start of two new contingency FCAS markets. The Very fast raise contingency FCAS market, and the Very fast lower contingency FCAS. Upon commencement of the VF FCAS market, a commissioning period of two weeks with an initial max requirement of...

Commercial and market outlook

Is the sun setting on utility solar?

The Federal Government has legislated emissions reductions of 43% below 2005 levels by 2030. Sourcing electricity from renewable technologies is fundamental to meeting this, with a much-publicised target of 82% renewables in the grid by 2030 – up from a current value of 38% over the last year. Fortunately, the...

Commercial and market outlook

The Very Fast FCAS market is about to commence – a look at a possible time-of-day profile for R1

On 9 October 2023, 1pm (market time), the dispatch of the new Very Fast (VF) FCAS market in the NEM will commence and will add two new markets for contingency FCAS, Raise 1 (R1) and Lower 1 (L1). AEMO has released a final industry go-live plan to keep track of...

Low carbon generation

“Ooh, a storm is threatening, My very [interconnection] today”: Can states utilise interconnection to share wind resources?

Penetration of renewables continues to dominate the energy news, as we saw renewables as a proportion of total demand reach new heights this week to a new record of ~70% penetration. In light of this continuing march toward a renewable-dominated grid (building on some analysis we did in Chart of...

Energy storage and flexibility

How long is the ‘Golden time of day’ for batteries?

A key part of the business case for grid-scale standalone batteries is the arbitrage opportunity between low daytime wholesale prices (when renewable energy generation from solar is plentiful) and high evening prices (when the sun goes down and household demand ramps up quickly). The share of battery revenue coming from...

Low carbon generation

MLF changes in NSW in the past decade

MLF, short for Marginal Loss Factor, represents the portion of electricity losses that occur along the transmission network between a connection point and the Regional Reference Node (RRN). Within the NEM, the MLF serves as a metric to quantify these losses along the network, playing a pivotal role in determining...