Proposed changes to PFR and the impact on battery operations

On 3 August, at the request of the Australian Energy Market Operator (AEMO), the Australian Energy Market Commission (AEMC) initiated a rule change request proposing to “clarify the mandatory primary frequency response (PFR) obligations of scheduled bidirectional plant (i.e. batteries with a capacity of 5MW and greater)”.

One of the proposals within the rule change request is that batteries enabled for FCAS should be required to provide PFR. The AEMO has stated that as well as increasing the availability of PFR, which will promote power system security, using batteries to supply PFR promotes economic efficiency.

It is unclear whether mandating the provision of PFR for batteries would promote either economic efficiency or security, as suggested by the AEMO. If the provision of PFR, relative to contingency enablement, follows a similar path to the regulation raise market, then it is likely that under this rule change, batteries will require higher contingency FCAS prices to compensate for the opportunity cost of discharging at suboptimal times of the day[1]. This means utilising energy that could be discharged at higher prices (evening peak) and utilising throughput that limits storage (mostly) to an average of once per day. In terms of promoting economic efficiency and system reliability, it also seems counterintuitive to mandate batteries to discharge during the middle of the day, often when electricity prices are at their lowest with an excess of energy being produced, reducing the available energy supply for the evening peak when prices are at their highest. In an environment where financing battery projects on a merchant basis is already challenging, this rule change will likely reduce the revenue streams available to batteries or, at the very least, add more complexity to estimating future revenue streams for battery projects. The potential impacts could be:

  • reduced revenues from contingency markets as battery operators decide to reduce enablement in these markets to conserve energy for the evening peak,
  • a reduction in arbitrage opportunities as energy is required during the middle of the day for the provision of PFR,
  • reductions in battery life because of increased cycling,
  • a reduction in participation in contingency and/or energy markets due to warranty restrictions for cycle rates, or
  • a combination of the above.

This Chart of the week looks at the participation of the Lake Bonney BESS in the regulation raise and contingency raise 6-second markets relative to regulation raise throughput[2]. The chart below details Lake Bonney’s average participation in the raise regulation and raise 6-second markets per hour (January 2022-August 2023) along with the average regulation raise throughput percentage[3].

As the requirement to discharge energy increases throughout the day (the grey line), the Lake Bonney BESS reduces its enablement of regulation FCAS and switches to the provision contingency FCAS. This is particularly pronounced between the hours of 8am and 5pm. Between 5-8pm the enablement of regulation raise FCAS increases despite the higher chances of being required to discharge. This is likely because there is little opportunity cost in discharging during the evening peak when energy prices are generally at their highest (see Figure 2 below). The hours with the highest participation in regulation raise are during the morning and evening peaks. Over the period, Lake Bonney, on average, discharged 46.8MWh per day to the grid, equating to a daily cycle rate of close to 1[4].

In the context of future intraday spreads[5], providing regulation raise in the morning and evening whilst sitting in the contingency raise markets during the day ensures energy is dispatched at the times where the value is highest (i.e. at the highest market prices). The rule change proposed by the AEMO has the potential to change this dynamic by requiring batteries that are enabled in contingency FCAS markets to provide PFR support. If the requirement of PFR follows a similar path to regulation raise, this would mean batteries discharging throughout the middle of the day, where the value of the energy is at its lowest. It would also mean battery operators would likely have to reduce participation in some markets to ensure cycle rates are within manufacturer warranties.

Cornwall Insight Australia provides technical advisory services on BESS projects, and our Storage Investment Model provides revenue stream forecasts (energy and FCAS) for 20 years. We also have a new quarterly subscription product, BESS investment benchmark, outlining future revenue opportunities for storage assets across 20 years for 2, 4, and 8 hours duration in all mainland states for COD 2025 and 2030, which breaks down revenues by market and provides an assessment of the different project financial metrics. For more information, please contact enquiries@cornwall-insight.com.au.


[1] Frequency Performance Payments would be another source of revenue

[2] Regulation raise is a secondary frequency response market where AEMO schedules, on a 4-second basis, enabled FCAS providers to discharge (raise) and charge (lower).

[3] For example, if a generator was enabled for 10MW and was instructed by AEMO to provide 5MW this would represent a 50% regulation raise throughput percentage.

[4] A degradation rate of 3% applied to 52MWh over 3.5 years of operation has been assumed.

[5] The difference between the lowest and highest price of electricity within the day


To keep reading, please log in to your account

Related thinking

Energy storage and flexibility

R1 and L1 revving up the BESS revenues

In our ‘The VFF… Very Fast and Financially rewarding market so far’ Chart of the week, the two new contingency markets, the Very Fast raise contingency FCAS market and the Very Fast lower contingency FCAS, were analysed and demonstrated the high participation of big batteries along with VPPs and DERs....

Low carbon generation

An investigation into REZ capacity factors during Victoria’s dark doldrums

As the grid transitions to much higher levels of renewable penetration, the range of generation outcomes on any given day increases. The worst of these ranges are known as dark doldrums when there is a combination of poor conditions for wind and solar generation, usually a windless day in winter....

Commercial and market outlook

The VFF… Very Fast and Financially rewarding market so far

On 9 October 2023, 1pm (market time), we saw the start of two new contingency FCAS markets. The Very fast raise contingency FCAS market, and the Very fast lower contingency FCAS. Upon commencement of the VF FCAS market, a commissioning period of two weeks with an initial max requirement of...

Commercial and market outlook

Is the sun setting on utility solar?

The Federal Government has legislated emissions reductions of 43% below 2005 levels by 2030. Sourcing electricity from renewable technologies is fundamental to meeting this, with a much-publicised target of 82% renewables in the grid by 2030 – up from a current value of 38% over the last year. Fortunately, the...

Commercial and market outlook

The Very Fast FCAS market is about to commence – a look at a possible time-of-day profile for R1

On 9 October 2023, 1pm (market time), the dispatch of the new Very Fast (VF) FCAS market in the NEM will commence and will add two new markets for contingency FCAS, Raise 1 (R1) and Lower 1 (L1). AEMO has released a final industry go-live plan to keep track of...

Low carbon generation

“Ooh, a storm is threatening, My very [interconnection] today”: Can states utilise interconnection to share wind resources?

Penetration of renewables continues to dominate the energy news, as we saw renewables as a proportion of total demand reach new heights this week to a new record of ~70% penetration. In light of this continuing march toward a renewable-dominated grid (building on some analysis we did in Chart of...

Energy storage and flexibility

How long is the ‘Golden time of day’ for batteries?

A key part of the business case for grid-scale standalone batteries is the arbitrage opportunity between low daytime wholesale prices (when renewable energy generation from solar is plentiful) and high evening prices (when the sun goes down and household demand ramps up quickly). The share of battery revenue coming from...

Low carbon generation

MLF changes in NSW in the past decade

MLF, short for Marginal Loss Factor, represents the portion of electricity losses that occur along the transmission network between a connection point and the Regional Reference Node (RRN). Within the NEM, the MLF serves as a metric to quantify these losses along the network, playing a pivotal role in determining...