Boulevard of Broken Plants: Can NSW reserves handle non-Green Days?

It’s been easy to get caught up in all the news from the Victoria and Queensland governments proposing record-setting funding and environmental targets by 2030 and 2035, along with the news of AGL bringing forward the closure of Loy Yang A. This signals that energy transition is now well and truly on. However, targets are one thing; what about replacing capacity pending retirement in the short term? The NEM struggled during the most recent Q2, driven by high input prices and some outages, culminating in the unprecedented market suspension. With the imminent closure of Liddell looming, how well prepared are we?

Cornwall Insight Australia’s most recent Energy Market Perspective explored future commodity prices and how well we were able to compensate for the outages in Q2 2022. In our report, NSW Q2 2023 was also identified as a hot spot for risk, with Liddell’s impending 1,500 MW of dispatchable capacity expected to be withdrawn by 1 April 2023. We previously discussed this topic almost two years ago when the closure was initially announced. In this Chart of the week, we take another look at reserve capacity for NSW based on this FY22 data and modelling the closure of Liddell, with a further hypothetical scenario should Eraring be unavailable.

Concerns over Liddell’s reliability have been apparent for years and were a large reason for bringing forward its eventual closure, and the last year provided evidence for this. Liddell’s three remaining units (after the retirement of Unit 3) have operated at just 55% of its maximum bid availability of 1,260 MW post-April 2022. Noting that although Liddell has a nameplate capacity of 1,500 MW, it has not submitted a full capacity bid since Unit 3 retired, preferring to operate at a comfortable baseload capacity of 350 MW per unit (83% of operating capacity) overnight and ~250-275 MW per unit (~60% of operating capacity) throughout the day in daytime pricing. Liddell was ramping to maximum during high-priced peaks occasionally.

Since the closure of Unit 3, the plant has had all three units operational 35% of the time, opting for a preferred two-unit operation 44% of the time. Despite these series of changes in operation techniques, Liddell still met ~8.3% of NSW’s total energy requirements this year (Liddell met at least 15% for NSW requirements until 2021).

Looking at reliability in peak periods since Unit 3 left the system and intervals where demand is > 10 GW (~13% of total), we see that the instances of NSW having a lack of reserves to meet peak demand are very limited. It is also important to note that NSW currently relies on other states to meet peak demand, needing to import at least 1,000 MW for 41.2% of the time, 500 MW for 77.8% of the time and 300 MW for 88% of the time. This illustrates a heavy reliance on importing energy during peak intervals to keep prices stable and energy flowing.

With reserves being ‘the ability of available supply to meet local NSW demand’, NSW had reserves of less than 1,000 MW available 10.5% of the time. Removing the availability of Liddell, NSW would have reserves of less than 1,000 MW for 16.8% of the time. For the sake of discussion and beginning to think about what the retirement scenario for Eraring may look like, given its closure is just around the corner in 2025, the removal of both Eraring and Liddell would leave less than 1,000 MW of reserve for 98% of the time (on FY22 data), with no reserves at all for 73.3% of the time. These figures highlight the expansion needed to replace the looming ~4 GW gap, as seen in our chart.

With only 60 MW of available large-scale storage in the state (Queanbeyan and Wallgrove BESS’), and the pipeline still being murky with only ~450 MW expected by mid-year next year, the ability to replace generation in times of need remains questionable.

The trifecta of Darlington Point batteries has the potential to be online in Q2 next year, but this is just 150 MW. Another 50 MW will come in New England and Broken Hill each. Neoen’s 100 MW Capital battery will likely have a commission schedule in early 2023. The 100 MW Sunraysia Emporium battery has a planned 2023 date, but the news here has quieted down. But all these are just enough to replace one unit of Liddell for a short time frame. While there are a number of other larger batteries, Tamworth and Armadale, together 300MW in the works and expected to be operational in 2024 (but have yet to reach financial close) and a number of larger projects announced for operation in 2025, including Eraring 700MW, Waratah 700MW, Uranquinty 200MW, and Liddell 700MW.

Outside of storage, the Kurri Kurri gas-fired station likely won’t be commissioned until 2024. There is the potential for another ~400-500MW’s of solar to come online, but this does little for peak time demand. The news on wind is not much better, with no public news on the state’s potential commissioning schedules next year.

However, history suggests that it is extremely difficult to get projects operational on time, and this has been exacerbated by the current market and grid conditions, leaving a potential for a significant shortfall in reserves should any further coal units (like Eraring) trip in the short term, but also leaves the market on the edge in 2025 should any of the current pipeline of storage or gas projects become delayed.

The closures of Liddell and Eraring also both hold the potential to have a large impact on the cap market. The remaining thermal capacity should be able to meet the requirements in the short term, but forward fuel markets and another cold autumn and spring hold the potential to cause a disturbance.

Other recent announcements by Queensland and Victoria are positive that investment is expected to pick up. However, there is a stark difference between focusing on the long-term 2030 compared to next year as some storage projects face delays and increased costs.

The question going forward remains: are we prepared for another cold Q2 as we should be? Forward markets for energy and commodities remain high, and slip-ups by the coal fleet at the wrong time can have significant consequences. Furthermore, the reliance on interconnector flow in peak demand can create risk.

Future prices give us some indication of how we will fare next Q2 (refer Chart 2). High fuel costs are likely to remain over the short/medium term, as evident in future prices. This is signalled by ACCC LNG netback prices of ~$50-60/GJ over the short term. Even sustained high gas prices of $40/GJ (Victorian and NSW cap price) translates to short-run marginal costs for gas peakers of around $400-560/MWh to break even (assuming a common standard heat rate of 10-14 GJ/MWh).


Maintaining sufficient available capacity, along with prices that are in the interest of both consumers and investors, will be one of the biggest challenges faced by the NEM as the retirement of aging coal power plants accelerates and the generation mix features increased levels of renewable generation.

There is plenty of work to be done and investment to be made. To help you do that, we have our Energy Market Perspective and other subscription services. For a demonstration or samples of our services, please contact us at enquiries@cornwall-insight.com.au.


To keep reading, please log in to your account

Related thinking

Energy storage and flexibility

R1 and L1 revving up the BESS revenues

In our ‘The VFF… Very Fast and Financially rewarding market so far’ Chart of the week, the two new contingency markets, the Very Fast raise contingency FCAS market and the Very Fast lower contingency FCAS, were analysed and demonstrated the high participation of big batteries along with VPPs and DERs....

Low carbon generation

An investigation into REZ capacity factors during Victoria’s dark doldrums

As the grid transitions to much higher levels of renewable penetration, the range of generation outcomes on any given day increases. The worst of these ranges are known as dark doldrums when there is a combination of poor conditions for wind and solar generation, usually a windless day in winter....

Commercial and market outlook

The VFF… Very Fast and Financially rewarding market so far

On 9 October 2023, 1pm (market time), we saw the start of two new contingency FCAS markets. The Very fast raise contingency FCAS market, and the Very fast lower contingency FCAS. Upon commencement of the VF FCAS market, a commissioning period of two weeks with an initial max requirement of...

Commercial and market outlook

Is the sun setting on utility solar?

The Federal Government has legislated emissions reductions of 43% below 2005 levels by 2030. Sourcing electricity from renewable technologies is fundamental to meeting this, with a much-publicised target of 82% renewables in the grid by 2030 – up from a current value of 38% over the last year. Fortunately, the...

Commercial and market outlook

The Very Fast FCAS market is about to commence – a look at a possible time-of-day profile for R1

On 9 October 2023, 1pm (market time), the dispatch of the new Very Fast (VF) FCAS market in the NEM will commence and will add two new markets for contingency FCAS, Raise 1 (R1) and Lower 1 (L1). AEMO has released a final industry go-live plan to keep track of...

Low carbon generation

“Ooh, a storm is threatening, My very [interconnection] today”: Can states utilise interconnection to share wind resources?

Penetration of renewables continues to dominate the energy news, as we saw renewables as a proportion of total demand reach new heights this week to a new record of ~70% penetration. In light of this continuing march toward a renewable-dominated grid (building on some analysis we did in Chart of...

Energy storage and flexibility

How long is the ‘Golden time of day’ for batteries?

A key part of the business case for grid-scale standalone batteries is the arbitrage opportunity between low daytime wholesale prices (when renewable energy generation from solar is plentiful) and high evening prices (when the sun goes down and household demand ramps up quickly). The share of battery revenue coming from...

Low carbon generation

MLF changes in NSW in the past decade

MLF, short for Marginal Loss Factor, represents the portion of electricity losses that occur along the transmission network between a connection point and the Regional Reference Node (RRN). Within the NEM, the MLF serves as a metric to quantify these losses along the network, playing a pivotal role in determining...